Early spring 2023: Conceptual approval by the CSU Board of Trustees (January 25, 2023); request for qualifications (RFQ) and request for proposals (RFP) released by SJSU for open bidding by general contractors and development firms.
-
-
What is the general timeline for this project?
-
Fall 2022: campus community outreach; demand surveys; preparation for presentation before the California State University Board of Trustees; beginning of California Environmental Quality Act (CEQA) environmental impact study process.
Early spring 2023: Conceptual approval by the CSU Board of Trustees; request for qualifications (RFQ) and request for proposals (RFP) released for open bidding by general contractors and development firms.
Spring to summer 2023: Awarding of contracts at the conclusion of the RFP selection process; development plan approval by the CSU Board of Trustees; design under way; CEQA complete.
Spring 2024: Design complete; permitting under way.
Later 2024: Construction under way.
2027: Construction complete; leasing under way.
-
-